From the factory side the choice is made earlier than the booking. When the shipping instruction reaches us, the credit is already issued and we prepare exactly what it lists. So far that has been full set originals every time. I have not yet seen a credit that names a platform.
So I would move your first question back to the sales contract. My understanding is that the eUCP applies only when the credit itself says so, so the wording must be agreed before the buyer applies to his bank. An amendment later needs the buyer and his bank to act, and I have watched shipments wait on that.
I am not sure of the legal side. But paper and a courier is a known cost. A rejected presentation is not.
Le Thu Ha, "paper and a courier is a known cost. A rejected presentation is not" is going on a sticky note above my desk.
I have never been paid against a credit. My buyers pay by transfer and nearly everything I send goes by air, where the waybill is not a document of title anyway, so nobody has ever asked me for originals. But a distributor I am talking to wants to move to sea freight and mentioned a credit. If the wording belongs in the sales contract, as you say, what do you actually write there? One sentence naming the eUCP, or do you also name the platform?
Thank you, Le Thu Ha, for putting the cost question so plainly. May I add how the same choice looks from an import desk at Nhava Sheva? Kindly note it is a parallel from Indian practice, not a credit rule.
Almost everything at our end now moves online, but the lines still want the original bills surrendered before they issue a delivery order. So when the bank's paper reaches the buyer late, the box waits at the terminal and storage and detention run while everyone watches the courier tracking.
That is the buyer's cost, not the exporter's, and it may be the argument that persuades him to settle the wording before he applies. Wishing your next presentation a clean first check.
Melody, the real issue here is that one sentence buys you a label, not a credit anybody can actually present against. The rules say the eUCP applies where the credit indicates it, and then they immediately ask for more.
First, the credit must indicate the format of each electronic record. Leave it out and any format may be presented, which sounds generous until the buyer's bank has to open it.
Second, it must indicate a place for presentation of the electronic records, and a separate place for any paper that still travels.
Third, the platform. As far as I can find, the rules never demand it by name. But a bill of lading is not a PDF you email; whoever holds control holds the goods. If the bank cannot receive control on the platform your carrier uses, the gap Renata describes lands on your shipment.
So the clause carries all three, agreed before the buyer applies. That is a payment terms checklist, and it belongs in your sales SOP before the first sea order, not after.