Melody, this is really a question about planning, not freight. The capacity squeeze just exposed it.
First, split the range by how fast each item actually sells, not by habit. The steady sellers can sit in a warehouse for a few weeks without hurting anyone, so they go by sea now. Air stays for reorders and for the items you genuinely cannot forecast.
Second, do not quietly move the promise. Move it openly. A buyer forgives a cutoff date printed in plain sight. A buyer does not forgive a parcel that arrives after the party.
Third, set your cutoff from the slowest leg you will actually use, then add a buffer, and write down who owns that date. I cannot give you a number that fits your lanes; the forwarder who wrote that note can.
The real issue here: a lead time model built on air was always a bet that the space would be there. Next year, put the sea fallback in your season plan before the market forces it on you.
Marcus, agree on the slowest leg, but I would look for it somewhere else. For a small brand moving off air, it is usually not the ship. It is the shed at the other end.
A few cartons by sea ride inside somebody else's container, and nobody touches them until the consolidator strips that box and sorts it by consignee. In December, at my port, everyone's Christmas is in the same queue. The ship arrives on time and the mugs sit behind a forklift.
Melody, before you set the cutoff, ask your forwarder how long their destination shed has been taking this month. Not the brochure figure. This month.
Otieno, and after the shed comes a truck. In December that truck is spoken for too, and the driver wants to be home. Not my lanes, Melody, but book the delivery leg when you book the ship, not when the box is stripped.